Water Infrastucture
Ipswich City Council Leakage and Pressure Management (Package 5)
- Installation of Flow Meters and Pressure Reducing Valves
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $1,000,000.00
Origin Alliance (Dinmore to Goodna)
- Water Main Relocation
- Property Connections and Water Meter Replacement
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $600,000.00
Eastern Bus Way Project (Leighton Contractors)
- Water Main Relocation
- Property Connections and Water Meter Replacement
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Mt Crosby Trunk Water Main Connection to SRWP Pipeline
- DN500 MSCL Water Main Installation
- Valve Pit and Thrust Block Construction
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Merrimac Waste Water Treatment Plant
- DN1610 MSCL Water Main Installation
- Valve Pit and Thrust Block Construction
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Port of Brisbane
- Water and Fire Reticulation (150-300mm Dia. HDPE)
- Valve and Pit Installation
Total Project Value of $1,000,000.00
Stormwater Infrastructure
Fulton Hogan Pacific Motorway Upgrade
- Installation of pump stations and commissioning of sewer/drainage systems for buildings.
- Installation of Fire main, Sewer Main, Non Potable and Potable water lines
Origin Alliance (Dinmore to Goodna) – Abi Group
- Twin DN1650 Installation
- Jacking of 1650 Pipeline
- Ecosoil Systems
- Maintenance Shaft Construction
Total Project Value of $480,000.00
Eastern Bus Way Project (Leighton Contractors)
- 3.8m x 4m RCBC Pipeline Construction
- 2700mm Pipeline Construction
- Ecosoil Systems
- Concrete Super Structures
- Tidal Management
- Live Connection
Total Project Value of $1,300,000.00
Logan – Ipswich Interchange Project (Leighton Contractors)
- DN1800 RCBC Installation
- DN3000 Pipeline Construction
- Jacking of 1800 Pipeline
- Concrete Pit Work
Total Project Value of $700,000.00
Merrimac Waste Water Treatment Plant (John Holland)
- DN1650 RCP Over Flow and Discharge Line
- Stormwater Harvesting and Treatment
- DN1800 Ecosoil Systems
- Valve Pit and Thrust Block Construction
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Various Developments for Delfin, Pensar and Civdec
- Sub Divisional Drainage
- Concrete Pit Work
- Culvert Installation
Gold Coast Desalination Alliance
- Roads and Stormwater Drainage
Total Project Value of $2,000,000.00
|
Sewage Infrastructure
Gallipoli Army Barracks Upgrade
- Installation of underground service networks including Natural Gas and Firefighting/Potable/Recycled Water
- Installation of HV and communication conduits, SCEC pits and upgrading of existing pits
- Installation of a fire fighting system including multiple pump sets, H-patterns and double pillar fire hydrants pump stations
- Installation of Flow Meter Pits, Reduced Pressure Zone Arrangements, Reflux/Check Valve arrangements
Total Project Value of $11.5 million
Gold Coast Desalination Alliance
- Plumbing of Complex Filtration Systems
- Chemical Dosing Facilities
Total Project Value of $1,000,000.00
Ipswich City Council G12 Pump Station Modifications
- Installation of Bypass Line
- Permanent DN1350 Pipe Work Installation
- Valve and Valve Pit Construction
- Wet Well Construction and Storage Facility
- Pump Station Fit-out
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Origin Alliance (Dinmore to Goodna)
- DN900 Plasti-Line Sewer Relocation
- Maintenance Shaft Construction
- Bypassing of Live Sewer
- Pressure Testing
- Live Connection
Total Project Value of $280,000.00
Eastern Bus Way Project (Leighton Contractors)
- DN800 PE Pipeline Relocation
- Property Connections and Water Meter Replacement
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $400,000.00
Merrimac Waste Water Treatment Plant
- DN1350 MSCL Pipework Installation
- Construction of Pump Station
- Pump Station Fit-out
- Concrete Pit Work
- Pressure Testing
- Live Connection
Total Project Value of $500,000.00
Gold Coast Desalination Alliance
- Internal and External Gravity Sewers (HDPE)
- Reinforced Concrete Pit Construction
- All Under Slab Drainage
Total Project Value of $2,000,000.00
G12 Sewer Pump Station
- Twin DN1800 RCP Inlet Works
- DN1350 Bypass and Flow Control
- DN600 MSCL Rising Main
- Concrete Valve Pits and Thrust Blocks
- Outlet and Over Flow Works
- Pump Station and Pump Station Fit-out and Live Connections
- Flow Meter Installation
Civil Structures
Merrimac Waste Water Treatment Plant
- Construct Reinforced Concrete Water Storage Tanks
- Construct Concrete Valve and Flow Meter Pits
Total Project Value of $500,000.00
Ipswich City Council Leakage and Pressure Management
- Construct Reinforced Concrete PRV and Flow Meter Pits
- Install Semi-Precast Concrete Pits
Total Project Value of $1,000,000.00
Eastern Bus Way Project (Leighton Contractors)
- Construct Reinforced Concrete Stormwater Super Structures
- Construct Large Scale Reinforced Concrete Sewer Chambers
Total Project Value of $400,000.00
Water, Sewage and Stormwater
Goodna Sewerage Treatment Plant Upgrade
- Installation of Pipelines ranging from 1440mm in diameter down to 32mm
- Installation of HV, LV and communication conduits, Pits and Rubble drains
- Importing over 40,000 tonne (16,000m³ Compacted) of fill in and around structures throughout the project.
- Installation of Chemical dosing lines within enveloper pipes, Install of the termination points and leak sumps.
- Managing flow controls and performing live connections into existing infrastructure
- Installation of Manholes, Scour pits, Chemical termination points
Total Project Value of $4.5 million
|